PRODUCTIVITY ANALYSIS OF EXCAVATOR AND DUMP TRUCK HEAVY EQUIPMENT ON DIGGING AND LOADING WORKS FLOOD CONTROL AFVOER WATUDAKON MOJOKERTO

Authors

  • Yudha Fatkur Rafi University of 17 Agustus 1945 Surabaya
  • Budi Witjaksana University of 17 Agustus 1945 Surabaya

DOI:

https://doi.org/10.26418/jtst.v23i2.61025

Keywords:

Dump Truck, Excavator, Flood Control, Productivity

Abstract

Heavy equipment is a vital resource in a project, but renting heavy equipment is a costly undertaking. Besides that, a project always has constraints that allow the project completion time to exceed the specified time, and delays will also cause costs incurred to increase. So from the calculation of the productivity of heavy equipment, it is necessary so that the tool can work optimally. From the analysis results, it was found that the productivity of excavators was 154.185 m3/Hour. For dump trucks, it was 37.99 m3/Hour, then calculating the duration of work. For heavy equipment excavators, it took 454 Hours, and for dump trucks, it took 263 O'clock. For the cost of renting heavy equipment from the calculation of the analysis of the cost of renting heavy equipment for excavators, a value of Rp.1,985,200/Day is obtained, while for dump trucks, it is Rp.2,578,000/Day

References

aktiar, Ario Yusuf. (2019). Analisa Produktifitas Penggunaan Units Berat Pada Pekerjaan Tanah Dan Pondasi Pada Proyek Pembangunan Gedung Pendidikan Profesi Guru Universitas Malang. Civil Engineering, 1999 (December), 133. http://eprints.itn.ac.id/1734/

Hutasoit, J. (2021). Produktivitas Penggunaan Units Berat Pada Proyek Pembangunan Jalan Tol Tebing Tinggi – Inderapura. Universitas Medan Area.

Kholil, A. (2012). Units berat: Units berat. In A. Kamsyach (Ed.), Isbn: 978-979692-080-8. PT. Remaja Rosdakarya.

Nugraha, S. A. (2020). Analisis Produktivitas Excavator Dan Dump Truck Studi Kasus Proyek Peningkatan Ruas Jalan Yogyakarta-Barongan (Imogiri), Bantul, Daerah Istimewa Yogyakarta.

Peraturan Menteri PUPR Nomor 1. (2022). Lampiran Peraturan Menteri Pekerjaan Umum Dan Perumahan Rakyat Nomor 1 Tahun 2022 (Issue 8.5.2017, pp. 2003–2005). jdih.pu.go.id

Suryana. (2012). Metodologi Penelitian : Metodologi Penelitian Model Prakatis Penelitian Kuantitatif dan Kualitatif. Universitas Pendidikan Indonesia, 1–243. https://doi.org/10.1007/s13398-014-0173-7.2

Sokop, R. M., Arsjad, T. T., & Malingkas, G. (2018). Analisa Perhitungan Produktivitas Units Berat Gali-Muat (Excavator) Dan Units Angkut (Dump Truck) Pada Pekerjaan Pematangan Lahan Perumahan Residence Jordan Sea. Jurnal Tekno, 16(70), 83–88.

Sutanto, K. R., Kosasi, M. H., & Andi. (2017). Produktivitas Units Berat pada Pekerjaan Galian Gedung P1 P2 UK Petra. Jurnal Universitas Kristen Petra, 1–8.

Teo, W. K., & Ling, F. Y. (2006). Predicting construction duration: A case of tower crane operations using artificial neural networks. Construction Management and Economics, 24(6), 611-622

Cheng, M. Y., Li, Q., & Lin, J. Y. (2012). Measurement of equipment productivity: A review. Automation in Construction, 22, 453-462.

Downloads

Published

2023-05-28